Case studies & projects
Each project shows how we handle complex situations with clear, precise and actionable diagnostics.
AsbestosPCBPAH
VaudYverdon Gymnasium – Buildings D, E, F
Full multi-pollutant survey before a school renovation.
Area
12'400 m²
Budget
33'500 CHF
Duration
6 weeks
Details
AsbestosLead
GenevaLe Léman Residence – 8 buildings
25-year asbestos management plan for 240 apartments.
Area
24'000 m²
Budget
62'000 CHF
Duration
10 weeks
Details
Asbestos
VaudSaint-Laurent Street 29
Survey before a bathroom renovation.
Area
800 m²
Budget
4'200 CHF
Duration
1 week
Details
5 pollutants
ValaisHospital Center – Technical Wing
Full survey before partial demolition (1962 wing).
Area
18'600 m²
Budget
89'000 CHF
Duration
14 weeks
Details
AsbestosHBCD
VaudLes Vergers Estate – 12 villas
Grouped survey before external insulation.
Area
3'600 m²
Budget
18'500 CHF
Duration
4 weeks
Details
5 pollutants
VaudRenens Factory – Conversion
Batiscan's largest mandate: industrial site → eco-district.
Area
42'000 m²
Budget
145'000 CHF
Duration
20 weeks
Details
Need a survey?
Describe the building, the planned works and the timeline. We will get back to you with the recommended scope of intervention.